92
Now on each single boiler of the cascade, on both control panels, the following two parameters must be selected
and programmed according to the above drawing.
Master:
C5
P5 DF
1
C2
P5 DA
0
Slave 1:
C5
P5 DF
0
C2
P5 DA
1
Slave 2:
C5
P5 DF
0
C2
P5 DA
2
And so on.
Menu C: Cascade
C 5
C a s S i / M a
0
Function for the cascading of the boiler(s).
This parameter sets the function of the boiler at a
cascade alignment
0 = Single / Slave unit
1 = Master unit
Menu C: Cascade
C 2
B u s a d d r e s s
0
Function for the cascading of the boiler(s).
This parameter determines the address of the boiler
for the total cascading control.
Master = 0, Slave1 = 1, etc.
When the correct parameter is set, this must be confirmed at the confirmation screen. After activation, the value will
blink for a few seconds while the parameter is programmed into the boiler.
PARAMETERS
PARAMETERS
PARAMETERS
PARAMETERS
master
slave 1
slave 2
slave 3
slave 4
slave 5
slave 6
slave 7
CASCADE
CONNECTION