Ensure that the correct space is provided when positioning the boiler for maintenance and replacement of
parts. The recommended minimum clearance is:
- Side clearance:
500 mm (advised 1000 mm)
- Front clearance:
800 mm
- Rear clearance:
500 mm
•
Make sure that the floor on which the boiler is placed can hold the weight of the boiler.
The following facilities are needed in the technical room:
•
One wall socket (electricity) with earth connection near the boiler
According to the valid standards and regulations a fire switch needs to be installed outside the boiler room; in case
of emergencies the electrical power to the boiler(s) can be shut off.
5.2.3
V
ENTILATION
Either when the boiler is connected independently or when it takes the combustion air out of the technical room, the
ventilation of the technical room needs to meet all applicable standards and regulations.
5.3
Removing the top, front and side panels
The top panel can be removed by loosening the screw on the middle of the control panel, if the top panel is removed
the side and front panels can also be easily removed by lifting them up and moving them away from the boiler. These
panels can only be removed if the top panel has been removed first!