Operation
SPECTRO GENESIS FES 27 — 17.07.2019
— 25
6.
Click the “START PLASM” button in order to activate the start of plasma.
The sample introduction system is automatically flushed with argon.
At the end of this process, the plasma is started.
7.
Click the “START PUMP” button in order to activate the peristaltic pump.
Depending on the application, distilled water or a zero solution ("blank"),
which is adjusted to the matrix, should be nebulized for approx. 10
minutes in order to heat up and equalize the components.
The instrument is now switched on and the plasma started.
5.4
Switch off the instrument/plasma
Information
Leave the instrument in standby mode whenever possible (main switch set to
"On". This ensures good long-term stability during the measurement).
To switch off the instrument, proceed as follows:
1.
Flush the sample introduction system for approx. 10 minutes with a suitable
blank solution, e.g., distilled water for aqueous applications.
This avoids crystallization in the sample introduction system.
2.
Select the “Solid State Generator” dialog in the instrument control parameter
dialog window. Switch off the plasma by clicking the "Plasma" button or
press the "Plasma Off“ button (blue button) on the right side of the instrument.
The plasma extinguishes.
3.
Press the “X” button in the upper right-hand corner of the application window
in order to end the instrument’s software program (ICP ANALYZER PRO).
The program is terminated.
4.
Select the dialog item "Shut down" in the “Start” menu of the operating system
and confirm the dialog box.
The computer is switched off.
Summary of Contents for FES 27