![SolarEdge SE3K-N4 Installation Manual Download Page 17](http://html1.mh-extra.com/html/solaredge/se3k-n4/se3k-n4_installation-manual_1313739017.webp)
NOTE
The DC bus of each unit is separate and not shared for all units. Therefore in addition to following the
inverter design rules, each unit should follow the unit design rules as detailed in the Technical
Specifications.
1. Connect the Minus (-) output connector of the string’s first power optimizer to the Plus (+) output
connector of the string’s second power optimizer.
2. Connect the rest of the power optimizers in the string in the same manner.
Figure 5: Power optimizers connected in series
3. If you intend to monitor the installation, using the SolarEdge monitoring platform, record the
physical location of each power optimizer, as described in
Providing Installation Information
WARNING!
Input and output connectors are not watertight until mated. Open connectors should be mated to
each other or plugged with appropriate watertight caps.
Three Phase Inverter with synergy technology Guide MAN-01-00402-1.1
16
Step 3: Connecting Power Optimizers in Strings