Figure 15: Marking the drilling holes locations
4. Place the mounting templates vertically against the wall and mark the drilling hole
locations for the bracket of the Synergy Manager. Make sure that the template
aligns with the two drilling holes marked A.
5. Drill two holes for each bracket and mount the brackets.
6. Position and secure the mounting brackets to the wall using at least two screws per
bracket. Tighten the screws all the way and verify that the brackets are firmly
attached to the mounting surface.
7. Mount the Synergy Units:
NOTE
When installing the Synergy Units, always install the center Synergy Unit first.
NOTE
The grounding wire can be installed on either side of the Synergy Unit
chassis. When installing three Synergy Units, connect the chassis grounding
wire to the center Synergy Unit before hanging the left or right Synergy
Units. Refer to: "Connecting Ground and AC Wires to the Synergy Manager"
Three Phase Inverters with Synergy Technology
32
Mounting and Connecting the Synergy Manager and Synergy Units
Summary of Contents for SE K Series