![SolarEdge SE K Series Installation Manual Download Page 26](http://html1.mh-extra.com/html/solaredge/se-k-series/se-k-series_installation-manual_1313719026.webp)
Indication
ON/ OFF/
P
switch
position
LED
Comment
FAULT
POWER
COMM.
Power
Optimisers not
paired
ON (1)
OFF
Blinking
S_OK: ON
No S_OK:
OFF
S_OK: ON
communication
with the
monitoring
platform is
established
Pairing
Blinking
Blinking
Blinking
Wake-up/ Grid
Monitoring
OFF
Blinking
Blinking
System
Producing
OFF
ON
S_OK: ON
No S_OK:
OFF
Night mode (no
production)
OFF
Flickering
S_OK: ON
No S_OK:
OFF
Inverter is OFF
(Safe DC)
OFF (0)
OFF
Blinking
Inverter is OFF
(DC not safe)
Blinking
Blinking
S_OK: ON
No S_OK:
OFF
Inverter
configuration
or reboot
ON / P
ON
ON
ON
Inverter
firmware
upgrade
ON / P
Alternating Alternating Alternating
The upgrade
process can take
up to 20 minutes
Error
Any
ON
ON/ OFF/
Blinking/
Flickering
ON/ OFF /
Blinking/
Flickering
and
Troubleshooting
on page 65
Chapter 3: Installing the Synergy Manager and Synergy Units
25
Three Phase Inverters with Synergy Technology
Summary of Contents for SE K Series
Page 74: ......