59
August 2020
|
Solar Stik
®
Inc.
PSS-G/RAID Alternative Energy System Deployment Guide
Figure 58. Generator status LED
18 Initialize and Calibrate the System
i. Press CTRL button.
ii. Rotate SELECT knob until the display shows “03 Gen Control”.
Press SELECT.
iii. Rotate SELECT knob until "Generator ON" appears in the display.
Press SELECT.
iv. “Remote Generator Start and Operation” sequence will begin. (Total process may take up to
3 minutes.)
v. Audible “Start-Warning” alarm sounds. (Audible alarms are located in the PRO-Verter 7000.)
NOTE:
The Audible “Start-Warning” alarm sounds (10 sec.) when the PRO-Verter
7000 is
connected to an MEP-802A TQG and the generator is about to start.
a Verify the green Ready LED is illuminated on the Faceplate of the PRO-Verter 7000
b Start the Generator with the PRO-Verter
Menu for generator control
01 ACIn Control
Auto Connect
CTRL
Press
Top line shows current
CTRL menu and position in CTRL menu.
Bottom line shows current setting.
Push SELECT to edit current setting.
Press to save
01 ACIn Control
03 Gen Control
ON
Set Gen Control
OFF
Set Gen Control
ON
Set Gen Control
AUTO
Rotate to
desired
selection:
02 CHG Control
Multi Stage