Figure 22. Generator control panel
Inverter on/off button
Inverter on/off LED
B System Activation
4. Turn on the main power switches on all Expander Paks and the PRO-Verter.
~The Power Hub turns on automatically when connected to the battery bank via the DC bus
(Inter-Connect network).
5. Verify the Inverter function engages. The LED next to “INV” will be illuminated when the inverter is
operating.
1. Connect loads to the PRO-Verter (If not already connected).
2. Verify the generator has fuel and oil and that the generator
starter battery cables are connected.
3. Turn on the generator MAIN SWITCH and AC BREAKER switch
by toggling it up (Figure 22, arrows).
Figure 23. PRO-Verter LCD control panel
Note:
The generator control panel is programmed for the L0
application and set to AUTO MODE. DO NOT use the buttons
on the generator control panel to control the generator.