Commissioning
12.4 Commissioning the 3RW40
SIRIUS 3RW30 / 3RW40
Manual, 01/2010, 535 1995-02 DS01
99
12.4.1
Commissioning procedure
1. Check the voltages and wiring.
2. Set the start and stop parameters (for recommended parameters, refer to the quick
commissioning table).
3. Set the motor overload function (if required)
4. Define the RESET mode if a failure occurs.
5. Start up the motor and if necessary optimize the parameters (refer to the quick
commissioning table).
6. Document the parameter settings if required.