The gas turbine is started in the "normal start" operating mode. The gas turbine is partly started
with upstream ventilation of the exhaust gas section and the boiler.
Operating mode
Power of the starting frequen‐
cy converter (SFC)
Load cycle
% of the SFC nominal power or
current at U
g
< U
n
-SFC
Operating time (min)
Ventilation
70
0
Pause
0
0
1. Normal start
100
4
Pause
0
2.5
Ventilation
70
0
Pause
0
0
2. Normal start
100
4
Pause
0
2.5
Ventilation
70
0
Pause
0
0
3. Normal start
100
4
Pause
0
2.5
Ventilation
70
0
Pause
0
0
4. Normal start
100
4
Non-operational period
0
120
It can be derived from the load cycles that the starting frequency converter is not dimensioned
for continuous operation at nominal power.
3.5.26
Duty cycle (option C62)
The starting frequency converter is dimensioned in such a way that the specified duty cycles can
be performed. The duty cycles are possible with the described operating modes without thermal
overload at maximum ambient temperature.
The gas turbine is started in the "normal start" operating mode. The gas turbine is partly started
with upstream ventilation of the exhaust gas section and the boiler.
Operating mode
Power of the starting frequen‐
cy converter (SFC)
Operating time (min)
% of the SFC nominal power or
current at U
g
< U
n
-SFC
at 40 °C
Ventilation
70
10
Pause
0
1
1. Normal start
100
4
Pause
0
2.5
Ventilation
70
10
Pause
0
1
2. Normal start
100
4
Description
3.5 Options
3rd Party LCI Control Upgrade
46
Operating Instructions, 02/2022, A5E31872818