O P E R A T I N G I N S T R U C T I O N S | ZIRKOR200 Ex-D
Subject to change without notice
INSTALLATION
5
5.9.6
Aligning the V-shield
Before installing the probe, determine flow direction (3) of the flue gas and turn V-shield (2)
of the filter against the flow of the flue gas.The V-shield can be freely rotated through 360°.
To do this, loosen locking screws (1) on the retaining ring, align V-shield (2) and retighten
the locking screws.
Fig. 10: Aligning the V-shield
5.9.7
Laying the probe cable and hoses
▸
Laying the cable and hoses - make sure no static electricity is generated.
▸
Connect to probe head.
▸
Connect the electronics unit.
WARNING: Danger of explosion through electrostatic charges
Static charges on the lines can cause an explosion.
▸
Protect lines against electrostatic charges.
▸
Lay lines in the Ex-area firmly, for example by means of cable trays.
NOTICE:
●
The system is not equipped with a power switch. A disconnecting device (e.g. a circuit
breaker) must be installed in the power supply line. The disconnecting device must
comply with local safety standards, be easily accessible, located in the immediate
vicinity of the system and clearly marked as the disconnecting device of the system
(on/off switch).
●
The probe cable is suitable for an ambient temperature of -40 °C to + 90 °C. All
other cables must be suitable for the ambient temperature on-site and have the
appropriate cross-section.
●
The connection terminals of the control unit are suitable for conductor cross-sections
from 0.08 mm² (AWG 28) to 2.5 mm² (AWG 12). Reduce the suitable cross-sections
by one size unit when using ferrules.