SY265C LC/SY265C LR Excavator OMM
4-38
Operation and Maintenance Manual — 0420
SANY
4. Lower the boom to raise the track.
NOTE:
Use cribbing to provide a firm surface if necessary.
5. Place cribbing under the track.
6. Raise the boom to lower the track onto the cribbing.
7. Drive the machine out of the mud.
Two Tracks Stuck
1. Position the boom and arm at an angle between 90° and 110°.
2. Pivot the upper structure to position the boom over the front of the machine.
3. Curl the bucket so the back of the bucket touches the ground.
4. Lower the boom to lift the front of the tracks.
NOTE:
Use cribbing to provide a firm surface if necessary.
5. Place cribbing under the tracks.
6. Raise the boom to lower the tracks onto the cribbing.
7. Cut the bucket into the ground in front of the machine.
8. Retract the arm as with normal excavating while driving the machine forward out of the mud.