ERECTING THE SYSTEM
16. When using the outrigger configuration at work heights above 24
ft (7.3 m), the v-brace must be tied into the structure. Using ¼” x 3”
screws, anchor the tie bracket to the structure in the middle of the
v-brace centering it in line with the mast assembly. Connect the
ratchet strap from the tie bracket to the v-brace as shown in the
diagram. Complete the assembly by placing tension on the tie strap.
Important: DO NOT OVERTIGHTEN THE TIE STRAP. Doing so could put
undue force on the anchor screws and substrate, decreasing the
effective pullout strength of the connection. (Fig. 3.19)
17. 6 ft (1.83 m) and 12 ft (3.66 m) masts can be joined together to reach
the maximum work height of 75 ft (22.9 m). Heights over 24 ft (7.3 m)
require mid-bracing every 16 ft (4.9 m) or less. Repeat the necessary
steps above to properly secure the mast to the structure with the
v-brace at the appropriate heights.
18. Referring to the layout plan, repeat steps the previous steps as
necessary to properly erect each mast assembly.
ERECTING THE OUTRIGGER CONFIGURATION (cont’d)
Fig. 3.18
Fig. 3.19
PULL-OUT FORCE FOR V-BRACE TIE BRACKET
Pullout Force for Each Screw [2 screws total]
250 lbs (113 kg) [500 lbs total]
Summary of Contents for PowerPole
Page 1: ...Operator s Safety Manual www reechcraft com powerpole P N 4026579...
Page 8: ...8 Section 1 GENERAL SYSTEM INFORMATION CLIMBING UNIT WITH PLATFORM SUPPORTS Fig 1 1 Fig 1 2...
Page 42: ...42 Section TRANSPORT STORAGE AND MAINTENANCE 7 inspection and Maintenance Logs...
Page 48: ...Reechcraft Inc 845 34th St N Fargo ND 58102 888 600 6160 www reechcraft com PowerPole...