ERECTING THE SYSTEM
3
1. Referring to the layout plan, examine the ground conditions to ensure
the surface can support the intended load of the system. Prepare the
base surface for erection, removing any debris, obstacles, or any other
conditions that could lead to injury during erection. Prepare the bearing
areas by leveling and/or compacting the ground surface. Add cribbing
or base plates to properly support the bearing force (Fig 3.1).
1. Erection should only be carried out under the direct supervision of
a competent person, and in compliance with all local, state, and federal
requirements.
2. Refer to the layout plan to determine the complete list of equipment
required for erection. Be sure all components have been inspected and
maintained in accordance with product labels on the unit and
information contained in this manual, or any other documents supplied
by ReechCraft technical team.
3. Based on the layout plan, determine the location of the standoff tie to
connect the top of the mast. Use a ladder to access the wall or obtain
roof access to arrive at the mounting location of the standoff tie.
4. Attach the tie securely to the structure using 4 1/4”x3” screws or
equivalent to provide pullout strength according to (Fig. 3.7). Be sure
to follow federal, state, and
local guidelines for safe wall
and roof access during
erection process.
GROUND PREPARATIONS
ERECTING THE STANDARD CONFIGURATION
Fig. 3.2
Fig. 3.1
GROUND PREPARATIONS
Base Plate Area
94 in2 (606 cm2)
Screw Stabilizer Area (each)
48 in2 (269 cm2)
Force at Base Plate
1000 lbs (450 kg)
Force at Outrigger Screw Stabilizers (each)
500 lbs (225 kg)
Summary of Contents for PowerPole
Page 1: ...Operator s Safety Manual www reechcraft com powerpole P N 4026579...
Page 8: ...8 Section 1 GENERAL SYSTEM INFORMATION CLIMBING UNIT WITH PLATFORM SUPPORTS Fig 1 1 Fig 1 2...
Page 42: ...42 Section TRANSPORT STORAGE AND MAINTENANCE 7 inspection and Maintenance Logs...
Page 48: ...Reechcraft Inc 845 34th St N Fargo ND 58102 888 600 6160 www reechcraft com PowerPole...