Pronar T682, Pronar T682/1
SECTION 5
5.20
Required maintenance
Reduce pressure in supply conduit.
Pressure in conduit can be reduced by pressing the head of the
pneumatic connection until resistance is felt.
Remove securing slide (1).
Hold the filter cover (2) with the other hand. After removing slide lock, the
cover is pushed off by the spring located in the filter housing.
The filter element and the filter body should be carefully cleaned and blown
through with compressed air. Assembly should be done in reverse order.
INSPECT
•
Every 3 months.
5.4.1 DRAIN WATER FROM AIR TANK
Required maintenance
Tilt drain valve stem (2) located in the lower part of tank (1).
The compressed air in the tank causes the removal of water to the exterior.
Released
valve
stem
should
automatically close and stop flow of
air from the tank.
Drain the tank located on the other
side of the trailer.
In the event, that the valve stem resists
returning to its setting, then the whole
drain valve must be unscrewed and
cleaned, or replaced (if it is damaged) -
see section
CLEANING DRAIN VALVE
.
FIGURE 5.11
Draining water from the tank
(1) air tank, (2) drain valve
Summary of Contents for T682
Page 4: ......
Page 5: ......
Page 10: ......
Page 11: ...SECTION 1 BASIC INFORMATION ...
Page 26: ...Pronar T682 Pronar T682 1 SECTION 1 1 16 ...
Page 27: ...SECTION 2 SAFETY ADVICE ...
Page 45: ...SECTION 3 DESIGN AND OPERATION ...
Page 53: ...SECTION 3 Pronar T682 Pronar T682 3 9 FIGURE 3 6 Electrical lighting system diagram ...
Page 64: ...Pronar T682 Pronar T682 1 SECTION 3 3 20 ...
Page 65: ...SECTION 4 CORRECT USE ...
Page 85: ...SECTION 5 MAINTENANCE ...
Page 111: ...SECTION 5 Pronar T682 Pronar T682 5 27 FIGURE 5 12 Trailer s lubrication points ...
Page 112: ...Pronar T682 Pronar T682 1 SECTION 5 5 28 FIGURE 5 13 Trailer s lubrication points ...
Page 128: ...Pronar T682 Pronar T682 1 SECTION 5 5 44 ...
Page 129: ...NOTES ...
Page 130: ... ...