2--1
Powerware BPIV Parallel Cabinet Installation and Operation
164201409 REV. B
101503
Installing the Parallel System
2.1
Preliminary Installation Information
WARNING:
Installation should be performed only by qualified personnel.
Refer to the following while installing the system:
•
Refer to Appendix A of this manual for installation drawings and additional
installation notes.
•
Dimensions in this manual are in millimeters and inches.
•
Do not tilt the cabinets more than
10
˚
during installation.
•
The conduit landing plates are to be removed to add conduit landing holes as
required. Plate material is 16 gauge steel (0.060 in. thick).
•
The cabinets must be installed on a level floor suitable for computer or
electronic equipment.
•
If perforated floor tiles are required for ventilation, place them in front of the
Parallel System. Refer to Table R in Appendix A for equipment weight and point
loading.
•
Details about control wiring are provided in the Parallel Cabinet installation
procedure. Drawing 164201409---2 and Table Q in Appendix A identify the
control wiring terminations.
2.2
UPM Cabinet Installation
To install the UPMs, refer to the Powerware BPIV UPS Installation and Operation
manual referenced in the Introduction to this manual.
2