2--7
Powerware BPIV Parallel Cabinet Installation and Operation
164201409 REV. B
101503
NOTE:
TB2 connections to the CAN must come from the first or last UPM (refer to
sheet 2 of drawing 164201409---2 in Appendix A.
9.
Route and connect CAN wiring to Parallel Cabinet terminal block TB2. The
CAN is wired serially (daisy chained) between terminal block TB4 in the UPMs
and the Parallel Cabinet.
10.
Route and connect Building Alarm 4 wiring to Parallel Cabinet terminal block
TB2. Building Alarm 4, from each UPM, is wired in parallel and connected to
the Parallel Cabinet.
11.
When wiring is complete, secure Parallel Cabinet by reinstalling all previously
removed panels.
12.
Remove CAN termination jumpers (J40) from UPMs between the terminated
UPM and the Parallel Cabinet (refer to sheet 2 of drawing 164201409---2 in
Appendix A, for terminated and non-terminated UPMs). CAN termination
jumpers are located on the Communication Server Board (CSB) in each UPM,
refer to paragraph 2.2.6
Installing Customer Connections
in the for access
instructions to the CSB and to sheet 2 of drawing 164201300---2 for jumper J40
location.
2.4
Initial Startup
Startup and operational checks should be performed only by authorized service
personnel. Contact service in advance (usually a two week notice is required) to
reserve a preferred startup date.
2.5
Completing the Installation Checklist
The final step in installing your Parallel System is completing the following
Installation Checklist. This checklist ensures that you have completely installed all
hardware, cables, and other equipment. Completing all items listed on the
checklist will ensure a smooth installation. You should make a copy of the
Installation Checklist before filling it out, and retain the original.
After your installation is complete, a service representative will be able to verify the
operation of your Parallel System and commission it to support your critical load.
The service representative cannot perform any installation tasks other than verifying
software and operating setup parameters. Service personnel may request a copy
of the completed Installation Checklist to be sure you have completed all
applicable equipment installation.
NOTE:
The Installation Checklist MUST be completed prior to starting the Parallel
System for the first time.