12.0 TEMPORARY NON-USE (EXTENDED OUTAGE)
12.1 Installed/Out-of-Service System
If an INSTALLED battery is expected to STAND IDLE longer than the storage period
recommended for the storage temperature (see Table 4.1 on page 9), treat as follows:
1.
Before taking the battery out of service, give it an equalizing charge according to
Section 8.3.1.
2.
After the charge, open the connections at the battery terminals to remove load from
the battery.
3.
Throughout the extended non-use period, give the battery an equalizing charge before
the end of the recommended storage intervals noted in Table 4.1. Disconnect the
battery from the charger between equalizing charges.
12.2 Return to Service
To return the battery to normal service:
1.
Reconnect the battery, the load and charger.
2.
Give the battery an equalizing charge as described in Section 8.3.1.
3.
Return the battery to float operation.
Summary of Contents for EnergyCell 1100RE
Page 1: ...EnergyCell RE High Capacity Battery Installation Guide and Owner s Manual...
Page 4: ......
Page 28: ...Page 18 Publication No US DDm IM 003 www enersysinc com November 2003 NOTES...
Page 29: ......
Page 66: ...BATTERY MAINTENANCE REPORT DDm DDS DDV DGX mSeries and SC...
Page 67: ...BATTERY MAINTENANCE REPORT DDm DDS DDV DGX mSeries and SC...
Page 69: ...30 www enersys com Publication No US VR OM 002 March 2008 NOTES...