Recommended Tools and
Equipment – Start-up
The following items are recommended for a smooth and successful
start-up:
• A tool kit containing common tools and these additional items:
– A cordless power drill with 1/2
"
nut driver and 3/16
"
hex-head bit
– Voltmeter
– Small electronics screwdrivers
– Wire strippers/cutters
– Cable ties
– Tape measure
– Adjustable pliers
• A laptop computer with Hyperterminal (PC) or ZTERM (MAC), to
interface with the control panel if the control panel doesn’t have a
touch screen.
• A copy of the layout and a start-up checklist for the person
performing the system start-up.
• Appropriate personal protection equipment (PPE) for each person
involved in the start-up.
Pre-start-up Inspection
• Site drainage:
Verify that all riser lids, external splice box lids, and
AX pod lids are level and above grade.
• Serviceability:
Verify that there is a minimum of two feet of space
between AX pods. Check for a useable water source within hose
distance of the system.
• System layout:
Verify that the component layout in the plans or
the system diagram matches the installed system and note any
differences between the plans and the installed system.
• Landscaping:
Check for landscape features that may cause long-
term maintenance issues:
– Trees planted on top of tanks
– Trees that could shed snow onto critical components,
such as control panels
– Risers, external splice boxes, and pods covered in bark or other
landscaping materials
• Circuit breakers:
Open the control
panel and verify
that all of the circuit
breakers are off.
• System access:
Remove lid bolts and
open all lids.
• AX100:
Verify that
the lid bolt boxes
and pressure gauges
have been removed
from the AX pods. If
not, remove them at this time. Verify that the lateral inlet valves in
the pods are open and the spray nozzle turbines are pointed up, as
shown below.