background image

After the refrigerant pipe is installed and  before the refrigerant pipe 
is connected to an ODU, inject nitrogen at a certain pressure and at 
the  same  time  from  both  gas  and  liquid  sides  (for  the  R410A 
refrigerant  model,  inject  40  kgf/cm2  nitrogen  (at  3.9  MPa))  for  a 
24-hour air tightness test.

Connect  the  refrigerant  pipe  to  the  gas  side  and  liquid  side  of  the 
ODU.  Use  a  vacuum  pump  to  vacuumize  the  gas  side  and  liquid 
side of the ODU.

Turn on/off the valve core of the ODU by using a 5 mm hex wrench.

If the one-way pipe length is less than 5 m (including 5 m), the 
refrigerant  charging  amount  is  determined  according  to  the 
nameplate.
If  the  one-way  pipe  length  exceeds  5  m,  the  supplementary 
refrigerant charging amount should be calculated  according to 
the pipe diameter and length of the liquid-side pipes of the IDU 
and ODU. See the table below for details.
Record the amount of refrigerant charged and retain the record 
for use during future maintenance.

Supplementary

Refrigerant Amount

Remarks

L is the one-way 

pipe length
L is the one-way 

pipe length

Diameter of

Liquid-side Pipe

0.0115 kg (L-5)

0.027 kg (L-5)

Model

53/71

90/105/120

/140/160

The  refrigerant  sealed  into  the  ODU  must  not  be  used  for 
vacuumizing.

Do  not  let  air,  dust,  or  other  particles  invade  the  pipeline 
system during installation of the connecting pipes.
Install the connecting pipes only when the indoor and outdoor 
units are secured.
Make sure to keep the connecting pipes dry during installation 
so that no water will enter the piping system.
Connecting  copper  pipes  must  be  wrapped  with  insulation 
materials  (thicker  than  10  mm,  the  thickness  should  be 
increased if the unit is installed in a closed humid place).

NOTE

Depending on the installation conditions, excessive torque will 
damage the pipe socket, while inadequate torque will cause air 
leakage. Refer to the following table to determine the tightening 
torque.

1. Bend  the  pipe  or  drill  a  hole  in  the  wall  as  needed.  The
cross-sectional  area  of  the  pipe  bending  deformation  must  not 
exceed  1/3  of  the  original pipe section.  A  protective  casing  should 

be  provided  at  the  wall  or  floor  hole.  The  weld  joint  must  not  be 
inside the casing. The drill hole on the external wall must be sealed 

and  tightly  wrapped  with  a  binding  tie  to  prevent  impurities  from 
entering the pipe. The pipe must be insulated with an insulation pipe 

of suitable size.

2. Insert  the  bundled  piping  and  wiring  from  outside  the  room

through the wall opening into the room. Be careful when laying out 
the pipes. Do not damage them.

After completing the above steps, the check valve stem of the ODU 
should be fully opened to ensure that the refrigerant pipeline of the 
IDU and ODU is unobstructed.
Use  a  leak  detector  or  soapy  water  to  carefully  check  for  leakage 

and ensure that there is no leakage. Cover the joint of the IDU with 
a sound/heat insulation sleeve (accessory) and wrap it tightly with a 
binding tie to prevent condensation and water leakage.

1. Flaring

2. Insert the pipe into the connection nut flare.

Align  the  connection  pipe,  tighten  the 
connecting  nut  with  a  hand,  and  tighten 

them with a wrench as shown in the right 
figure.

Use  a  pipe  cutter  to  cut  off  the  pipe,  and  rotate  the  pipe  cutter
repeatedly to cut off the pipe.

If  a  copper  pipe  purchased  from  the  market  is  used,  the  heat 
insulation  material  of  the  copper  pipe  must  be  the  same  (thicker 

than 10mm, the thickness should be increased if the unit is installed 
in a closed humid place).

Method of unwinding the coil: 
Straighten the pipe end

Pipe cutter

Rough

Slope

Burrs

90 degrees

Outer diameter 

(mm)

Max.

Min.

A (mm)

8.7

12.4
15.8

8.3

12.0
15.4

19.0

18.6

23.3

22.9

90 degrees ± 4

R0.4~0.8

A

Pipe size

Tightening torque N.m

14.2 17.2 N.m  (144 176 kgf.cm)

32.7 39.9 N.m  (333 407 kgf.cm)

49.5 60.3 N.m  (504 616 kgf.cm)

61.8 75.4 N.m  (630 770 kgf.cm)

97.2 118.6 N.m  (990 1210 kgf.cm)

CAUTION

CAUTION

10

Summary of Contents for OTEC IECS-D Series

Page 1: ......

Page 2: ...sconnection device which has at least 3mm separation distance in all pole and a residual current device RCD with the rating of above 10mA shall be incorporated in the fixed wiring according to the nat...

Page 3: ...requirement 18 Vacuum pump Charge hose R410A special requirement 19 Torque wrench 20 Copper pipe gauge adjusting projection margin 21 Vacuum pump adapter Required tools for installation work 1 Philip...

Page 4: ...ry if the location is not strong enough Carry out the specified installation works to prevent strong winds or earthquakes Improper installation may cause the unit to drop leading to accidents Before w...

Page 5: ...ling when necessary b Adjust the position of the unit and make sure that the gap with the ceiling is evenly spaced on all four sides of the unit and the base of the unit is 10 12 mm into the base of t...

Page 6: ...therwise it may cause water to leak Calibrate the levelness of the IDU using a spirit level or polyethylene tube filled with water The IDU is equipped with a built in drain pump and float switch Do no...

Page 7: ...ook Drainage pan hook Hook screw Phillips screwdriver Swing motor Foam at panel side Unit Ceiling Panel Panel bubble 1 Air outlet Air deflector Panel bubble 2 4 6 mm The plastic cover plate protruding...

Page 8: ...outdoor unit and the indoor unit may not exceed the allowable piping length In the case that the installation place is exposed to strong wind such as a seaside make sure the fan operating properly by...

Page 9: ...from becoming loose When the outlet of the water discharge pipe is higher than the pipe connection for water suction try to keep the water discharge pipe as vertical as possible and the water outlet c...

Page 10: ...nical surface of the connecting nut the refrigerant oil used must be compatible with the refrigerant of this model and screw it 3 to 4 turns with your hand to tighten it as shown in the Fig 3 9 When c...

Page 11: ...ge Refer to the following table to determine the tightening torque 1 Bend the pipe or drill a hole in the wall as needed The cross sectional area of the pipe bending deformation must not exceed 1 3 of...

Page 12: ...e or valve No power cable is attached to this equipment The user can select the power cable by reference to the stipulated power supply specifications No joint of wires is allowed Upon completion of w...

Page 13: ...ng issues before trial operation and the box for the confirmed items Perform the trial run only after the outdoor unit has been powered on for over 12 hours Check that all valves are opened before tri...

Page 14: ......

Reviews: