42
Chapter 4 Standard Tasks
Lift the Booklet maker Main Deck
[19]
Step
Action
Information
1
Open the connecting bridge
cover.
(
see ‘Open the Connecting Bridge
Cover’ on page 36
)
2
Open the folder cover.
(
see ‘Open the Connecting Bridge
Cover’ on page 36
)
3
Lift the clincher frame.
(
see ‘Lift the Clincher Frame’ on
page 39
)
4
Open the gathering area cover. (
see ‘Lower the Clincher Frame’
on page 39
)
5
Lift the Booklet maker main
deck.
The main deck lifts to
approximately 60º. The weight of
the main deck is supported by a gas
strut. Let the gas strut control the
movement of the main deck.
Summary of Contents for BLM 500
Page 1: ...BLM 500 Bookletmaker 50 User manual Operating information ...
Page 5: ...5 Chapter 1 Introduction to the Booklet maker ...
Page 19: ...19 Chapter 3 The User Interface ...
Page 48: ...48 Chapter 4 Standard Tasks Operate the Booklet maker offline ...
Page 88: ...88 Chapter 5 Error Conditions Problems and Solutions Manually park the Shuttle ...
Page 89: ...89 Chapter 6 Maintenance ...
Page 112: ...112 Chapter 6 Maintenance Install New Stitch Wire ...
Page 113: ...113 Appendix A Specifications ...
Page 116: ...116 Appendix A Specifications Specifications ...