Installation and Mounting
Installation and mounting must be effected in compliance with VDE 0100 /
IEC 364. Because it is an IP30 module, you must install it in a cabinet.
Please ensure a maximum ambient temperature of 60 ºC for reliable
operation.
2.1
Mounting orientation
The NETLink PRO ETH can be installed in any orientation.
2.2
Minimum clearance
Minimum clearances must be observed because
•
then it is possible to insert and remove the NETLink PRO ETH
without having to remove other system components.
•
there is enough space to connect existing interfaces and other
contacts using standard commercial type accessories.
•
there is room for any necessary cable routing.
For the NETLink PRO ETH, a minimum clearance of 60 mm must be left
above and below and 10 mm at the sides.
2.3
Installing the module
A wall/DIN rail bracket is available as an accessory for mounting on flat
surfaces or on DIN rails.
The available accessories are listed in Section 3.5 with the corresponding
order numbers.
Before you start
installation work, all
system components must
be disconnected from their
power source.