![NEC UNIVERGE SL2100 Hardware Manual Download Page 76](http://html1.mh-extra.com/html/nec/univerge-sl2100/univerge-sl2100_hardware-manual_3916628076.webp)
1.
Assemble the FM/WM Base-F, Base-R and WM Support.
WM Support
FM/WM Base-R
FM/WM Base-F
Figure 2-39 Bases and Support of the Battery Box
2.
Refer to
Figure 2-40 Floor-Mount Spacing Guide on page 2-30
drilling holes for 10 mm (0.394″) anchor bolts (locally procured).
Mark and drill the four holes required to install the FM/WM Base.
3.
Using anchor bolts, secure the FM/WM Base to the floor.
Four Anchor bolts
M10 mm (0.394″)
Front side
Front side
: Maintenance space
Wall
150
mm
(5.9
06″)
150 mm
(5.906″)
460
mm
(18
.110
″)
460 mm (18.1
10″)
AC inlet
side
AC inlet
side
500 mm (19.685″)
190 mm
(7.480″)
Anchor bolt location
Figure 2-40 Floor-Mount Spacing Guide
SL2100
ISSUE 1.0
2-30
Installation
Summary of Contents for UNIVERGE SL2100
Page 1: ...Hardware Manual GVT 010793 201 00 EU ISSUE 1 0 May 2017...
Page 14: ...MEMO SL2100 ISSUE 1 0 xii Hardware Manual...
Page 20: ...MEMO SL2100 ISSUE 1 0 R 6 PRODUCT LIABILITY...
Page 24: ...MEMO SL2100 ISSUE 1 0 R 4 Regulatory...
Page 164: ...MEMO SL2100 ISSUE 1 0 4 16 Maintenance...