Installing Server
3-15
Steps to Install the Rack-mount Model to the Tower Conversion Kit
Follow the procedure below to install the devices to the tower conversion kit.
1.
Open the front door of the tower conversion kit.
If the door is locked, use the server-accessory key
to unlock.
2.
Confirm the spots to fix 8 core nuts on the front
of the chassis.
See the figure on the right for where to fix
the core nuts
(4 on the front top and 4 on the front bottom.)
8 core nuts have been installed on the front of the
chassis.
3.
Insert the bracket from the front of the conversion
kit. Tuck the bracket firmly to the back.
Tower conversion kit (on the front bottom)
Tower conversion kit (on the front top)
Summary of Contents for EXP320K
Page 11: ......
Page 38: ...1 22 Before Using This page is intentionally left blank ...
Page 80: ...4 20 ESX Server Setup 1 10 Enter LUN Hex select 00 1 11 Select Boot LUN select 01 ...
Page 108: ...5 16 Procedures after Completion of Installation This page is intentionally left blank ...
Page 112: ...6 4 Troubleshooting This page is intentionally left blank ...
Page 114: ......
Page 115: ......