Electrical connection
*INSTALLATION*
145
Peak-load negotiation
The machine is suitable for use in an energy management system. For
this purpose, it must be technically adapted and the controls reset by
Miele Service.
Please contact Miele Service for further information.
Peak-load
management
In the event of a peak-load negotiation, some machine components,
such as the heater element, will be switched off for a while. The
machine will remain on during this period and the current program will
not be interrupted. If one of the components that is switched off is
needed during the current program stage, the program cycle time will
simply increase for the duration of the load negotiation.
The third line of the display will alert you to the peak-load negotiation,
for example:
Universal
Temperature
Peak load cut-out
75 °C