For the A-series type of mini chiller, the inter-connecting pipes between the two
compartments are the refrigerant pipes. For the B-series type, there is a water pipe in
between the two compartments.
Therefore, the detached installation of the A-series mini chillers is very similar to the
installation of a
split type air-conditioning
unit.
Note:
Gas line to be insulated with
tube insulation. Use the
correct size for each pipe, thickness
¼
”
Refrig. Pipe size
Liquid Gas
AC 040A
3/8” ¾”
AC 050A
3/8” ¾”
AC 058A
½” ¾”
Take care of the following items [for detached A-series installations]:
Maximum pipe length,m
AC 040C
20
AC 050C
20
AC 058C
20
a) Do not allow excessive refrigerant pipe
length between the two compartments.
Always choose the shortest path.
Long piping will cause high pressure
drops and reduces the capacity of the
system. Use the following
recommendations:
Maximum elevation, m
AC 040A
10
AC 050A
10
AC 058A
10
b) It is possible to have the hydraulic kit
higher or lower than the refrigerant
compartment. Do not allow excessive
elevation between these two
compartments. Use the following
recommendations:
If the elevation exceeds the above recommendations, care must be taken to ensure sufficient oil
return
to the compressor. Use oil traps (one every 30ft height interval) or oil separators, if
necessary.
c) The longer pipe lengths will require more refrigerant charge for optimum
performance.
Recommendation: Additional 50g (R-22) for every 1 meter of connecting pipe length.
Similarly, additional refrigerant oil charge may be required.
Section 1
Page 7
Summary of Contents for AC 40A
Page 1: ...AM MAC ...
Page 153: ...Appendix 1 ...
Page 154: ...Appendix 2 Appendix 2 ...
Page 157: ...GRAPH OF PRESSURE DROP VS FLOW FOR VARIOUS C V RATINGS Appendix 5 1 ...
Page 158: ......
Page 159: ...Water Capacity Graph Appendix 5 2 ...
Page 160: ...CHART 3 FRICTION LOSS FOR CLOSED PIPING SYSTEMS Appendix 6 1 ...
Page 161: ...CHART 4 FRICTION LOSS FOR OPEN PIPING SYSTEMS Appendix 6 2 ...
Page 162: ...CHART 5 FRICTION LOSS FOR CLOSED AND OPEN PIPING SYSTEMS Appendix 6 3 ...
Page 168: ...Appendix 8 Appendix 8 ...
Page 169: ...Appendix 8 1 ...
Page 170: ...Appendix 8 2 ...
Page 171: ...Appendix 8 3 ...
Page 172: ...Appendix 8 4 ...
Page 173: ...Appendix 8 5 Appendix 8 5 ...
Page 174: ...Appendix 8 6 Appendix 8 6 ...
Page 175: ...Appendix 8 7 Appendix 8 7 ...
Page 176: ...Appendix 9 ...
Page 178: ...Appendix 11 1 Appendix 11 1 ...
Page 179: ...Appendix 11 2 Appendix 11 2 ...
Page 180: ...Appendix 13 ...
Page 181: ...Appendix 13 1 ...
Page 182: ...Appendix 14 Appendix 14 ...
Page 183: ...Appendix 15 1 Appendix 15 1 ...
Page 186: ...Appendix 17 Appendix 17 ...
Page 187: ...Appendix 18 ...
Page 188: ...CE20DW CE25DW Note PRESSURE DROP CORRECTION FACTOR 1 2947 0 0021 EWTºF Appendix 19 ...
Page 189: ... 2003 McQuay International 603 55194922 www mcquayup com ISO 9002 REGISTERED ...