![Malmet ES915 Operation, Maintenance And Installation Manual Download Page 11](http://html2.mh-extra.com/html/malmet/es915/es915_operation-maintenance-and-installation-manual_3918624011.webp)
Malmet Bedpan / Urinal Bottle Washer Disinfector (ES-D)
Detergent Model with Hands Free Operation
Operation, Maintenance and Installation Manual
Issue 5
Page
10
June 23
2.0
Installation and Commissioning
2.1
Installation
To avoid problems with this device, these Installation Guidelines should be followed.
Installations must be carried out by a qualified and licenced tradesperson.
The device must be affixed to the building structure to ensure mechanical stability prior to use. The device can be affixed
to the building structure via the holes provided in the device feet, or use of an appropriately rated appliance safety strap.
Prior to installation of the device, services as noted are to be provided by the facility. It is not the responsibility of Malmet
to provide these service connections.
Overcurrent protection device-
•
A 10A circuit breaker or fuse for 10A rated models must be installed in the building installation.
•
A 20A circuit breaker or fuse for 20A rated models must be installed in the building installation.
Risk Assessment
It is recommended a risk assessment is conducted by the user both prior to and after installation and any risks identified
mitigated to an acceptable level using the hierarchy of control;
https://commons.wikimedia.org/w/index.php?curid=55610678
Handling
Weights of Device:
Net: 92 kg
Shipping: 110 kg
Shipping with crating: 151 kg.
•
Handling of the device to installation site must be with fork lift or hand pallet truck.
•
Before unpacking device inspect carton for any damage relating to forklift forks and damage relating to device falling
over or for evidence of top loading
•
After unpacking the device, inspect all external panels for damage.
•
Remove the 4 screws holding the device to the pallet.