This section provides information to consider before installing
the J85502C-1 rectifier in a Lineage
®
2000 Battery Plant. This
section also describes the input and output wiring required and
the recommended procedure for installing the rectifier from
uncrating through startup. Lucent Technologies offers
“turn-key” engineering and installation services for the products
described in this product manual. Consult your Lucent
Technologies representative for details.
Safety
Please read Section 4, Safety, thoroughly before installing the
J85502C-1 rectifier, and carefully read and follow the
admonishments as they are presented throughout this
documentation.
Preparing for
Installation
Location of the J85502C-1 rectifier and associated equipment
must conform to the specific plans of each Lineage
®
2000 plant
installation. Physical, thermal, and electrical specifications are
given in Section 2. These specifications must be considered in
the plans for any installation that includes this rectifier.
Handling
Equipment
Each J85502C-1 rectifier weighs at least 240 pounds. Therefore,
the customer must make prior arrangements for appropriate
material handling facilities and equipment to unload, uncrate,
and set up the rectifier. Proper handling is necessary to assure
personnel safety and protect the equipment. Each rectifier, that
is not part of a battery plant when it leaves the factory, is shipped
in a tri-walled corrugated cardboard container secured to a
wooden shipping skid. The container should be moved by a
forklift.