Lucent Technologies Galaxy Power System 4804AP H569-450
11 - 44 Installation
Issue 1 June 2000
Power Up and Installation Completion
Initial System
Checkout and
Preparation for
Power Up
Prior to installing converters (if equipped) and rectifiers, verify
that the
correct ac voltage is present at the ac connectors in the
rectifier shelves.
Note: Disregard if this was done as part of the
AC Connection and
Wiring procedure.
Some of the following procedures are performed while ac voltage is
present at the cabinet; exercise extreme caution and observe all
precautions described in the safety section of this product manual.
Refer to the following figures for illustrations of the controller front
panels:
Figure 11-29: Vector
Figure 11-30: Millennium