The Alarm Test provides a means of testing the operation of any or all
of the system alarm relays and their wiring to the connected alarm
system. The test cannot be performed if any alarms are active. In
addition, Rectifier HVSD (High Voltage Shut Down) and RFA
(Rectifier Fail Alarm) tests can be included. For additional information,
consult the appropriate Galaxy controller product manual.
Connecting to
Load
The system is ready to connect to using equipment. Install or
turn on
load protectors when needed.
Galaxy Millennium Controller System Alarm Test
Step
Action
1
Connect all office alarm wiring from the controller’s office
alarm terminal block to the office alarm monitoring system.
2
Enable the alarm test feature.
Note: Both the Galaxy Millennium controllers have factory
hardware and software switches to enable the alarm test feature.
•
Hardware:
–
For the Millennium controller, enable a DIP switch on
the BSH board.
•
Software:
–
For the Millennium controllers, use the following key
sequence to get to the menu with the software switch:
Menu
→
Config
→
Alarm
→
TEST ALA : ON (H,S)
3
Once the Alarm Test feature has been enabled:
•
For the Millennium controller, use the front panel key
sequence Menu
→
Maint Oper
→
Alarm Test
→
Enter to
start the Alarm Test.