6 Commissioning/Start-up/Shutdown
33 of 104
mini-Compacta
2317.886/16-EN
6.2.2 Supply voltage
CAUTION
Wrong supply voltage
Damage to the lifting unit!
▷
The maximum permissible deviation in supply voltage is 10 % of the rated
voltage indicated on the name plate.
6.3 Prerequisites for commissioning/start-up
NOTE
The control unit parameters have been set at the factory. The parameters need not
be changed for commissioning.
Ensure that the following requirements are met prior to commissioning/start-up:
▪
The sewage lifting unit has been properly connected to the electric power supply
and is equipped with all protection devices.
▪
All relevant VDE standards and country-specific regulations are complied with.
▪
The safety regulations are complied with and the technical data of the sewage
lifting unit is suitable for the unit's intended use.
▪
The sewage lifting unit has been installed properly. All transport locks have been
removed.
6.3.1 Lifting unit with LevelControl Basic 1
DANGER
Control unit cover not closed properly
Danger to life!
▷
After making the collecting tank settings, properly close the cover of the
control unit.
▷
After properly closing the cover of the control unit, plug the mains plug into
the power supply.
Steps required for commissioning:
1. Set the parameter for the inlet nozzle to be used (recommended).
2. Connect the rechargeable battery.
3. Check the direction of rotation.
4. Test the lifting unit for correct function and leak-free operation.