3-24
PC210/240-ENG
23. MAINTENANCE SCHEDULE CHART
SERVICE ITEM
PAGE
(EVERY 500 HOURS SERVICE)
Replace hydraulic tank breather element
3-60
EVERY 1000 HOURS SERVICE
Change oil in swing machinery case
3-61
Check oil level in damper case, add oil
3-62
Check all tightening parts of turbocharger
3-62
Check play of turbocharger rotor
3-62
Replace hydraulic filter element
3-63
Check and adjust valve clearance (1
st
1000 hour only)
3-63
Check fan belt tensioner bearing, belt and fan hub
3-64
Check fan belt tension
3-64
EVERY 2000 HOURS SERVICE
Change oil in final drive case
3-65
Clean hydraulic tank strainer
3-66
Clean, check turbocharger
3-67
Check alternator, starting motor
3-67
Check vibration damper
3-67
Change antifreeze
3-67
Check and adjust valve clearance
3-67
EVERY 4000 HOURS SERVICE
Check water pump
3-68
EVERY 5000 HOURS SERVICE
Change oil in hydraulic tank
3-69
23.2 MAINTENANCE WHEN USING
HYDRAULIC BREAKER
For machines equipped with a hydraulic breaker, the hydraulic oil
deteriorates faster than for normal bucket digging operations, so set the
maintenance intervals as follows.
•
Replacing hydraulic filter element
On new machines, replace the element after the first 100 to 150 hours,
then carry out further replacement of the element according to the ta-
ble on the right.
•
Changing oil in hydraulic tank
Change the oil according to the table on the right.
Summary of Contents for PC210
Page 2: ......
Page 44: ...1 32 PC210 240 ENG MEMO ...
Page 45: ...2 1 PC210 240 ENG OPERATION ...
Page 146: ...2 102 PC210 240 ENG ...
Page 147: ...3 1 PC210 240 ENG MAINTENANCE ...
Page 167: ...3 21 PC210 240 ENG 22 PERIODIC REPLACEMENT OF SAFETY CRITICAL PARTS m n ...
Page 220: ...3 74 PC210 240 ENG ...
Page 221: ...4 1 PC210 240 ENG SPECIFICATIONS ...
Page 231: ...4 11 PC210 240 ENG 25 SPECIFICATIONS ...
Page 232: ...4 12 PC210 240 ENG ...
Page 233: ...5 1 PC210 240 ENG OPTIONS ATTACHMENTS ...
Page 266: ...5 34 PC210 240 ENG 5 32 ...