Basic Finishing 6: MCVST42 With MQZCV42DD & Stone, Brick, or Tile Boarder
Step One:
Remove Non-Combustible Header Strip. Frame
Fireplace with nailing tabs oriented as shown.
Step Two:
Do not use Non-Combustible Header Strip on
top frame of fireplace. Use Concrete Board.
NOTE:
Wall will be flush with fireplace face.
Step 3:
A stone, brick, or other non-combustible border
may be applied to the wall. Maintain clearances from
fireplace opening below.
IMPORTANT NOTE!
When installing stone, brick, or other
material around the perimeter of the surround:
You MUST Leave 2-9/16” of the fireplace face exposed around
the fireplace opening on the Sides, 2” at the Bottom, and 3-
1/8” must be exposed on the top. This is to install and remove
the Door Frame. See drawings below.
A Tile Lip Kit (ZCV-TLK) is available.
Nailing Tab
Concrete Board
2
-9
/1
6
” M
IN
Fireplace
Opening
Drywall
3-1/8” MIN
Stone, Brick, Tile, etc.
Remove Non-Combustible
Header Strip
Back Frame of
MQZCV42DD Door
Required Clearance
MQZCVDD Door
(Continued)
21
Summary of Contents for MCVST42LP
Page 17: ...Fireplace Opening Required Clearance S1PF Surround 17...
Page 22: ...22...
Page 55: ...Gas Conversion for Modulator PART C 55...
Page 60: ...Configuration 1 Basic manual HI LO and manual ON OFF capabilities 60...
Page 61: ...Receiver Module 584 523 521 221 1001 P221SI Receiver Module 584 523 521 221 1001 P221SI 61...
Page 68: ...Proflame 2 Remote Control 68...
Page 70: ...70...