1. Connect the interface cable from the RP7900 unit to the SDS unit.
2. Connect the output of the RP7900 series to the input of the SDS unit.
3. Connect the output of the SDS unit to the device under test (the load).
4. If remote sensing is used, do NOT bundle the sense wire-pair together with the load leads; keep
the load wires and sense wires separate.
5. Install the bus bar
. Depending on how the units are wired, you may need to remove
the bus bar cut-outs from the safety covers.
Connections with Paralleled Units
The limiting factor as to how many Keysight RP7900 units you can connect to one SDS unit is the
current rating of the SDS relays, which is 60 A. For example, you can connect one 500 V, 10 kW unit
and one 500 V, 5 kw unit to one SDS unit and still be within the maximum current rating of 60 A.
l
In a master/slave configuration, connect the SDS interface cable to the
master
RP7900 unit.
l
For detailed connection information for paralleled units, refer to
l
If remote sensing is being used, connect the sense leads of both RP7900 units to the RPS sense
terminals on the SDS unit.
l
If multiple RPS units are used in a paralleled group, each 60 A group will require its own dedicated
SDS unit.
External Control Connections
Several customer-configurable functions are available on the rear panel of the SDS (see
the SDS Using Externally Wired Controls
). The connectors and pin-out functions are described as
follows:
Remote Interface (M12) Connector
Rear panel pinout view
Typical connections
Appendix A Keysight SD1000A Safety Disconnect System
306
Keysight RP7900 Series Operating and Service Guide
Summary of Contents for RP7900 Series
Page 1: ...Keysight Regenerative Power System RP7900 Series Operating and Service Guide ...
Page 2: ......
Page 100: ......
Page 262: ......
Page 314: ......