Step 3. Select the first calibration point. Measure the voltage across the sharing connector and enter
the data.
Front Panel Menu Reference
SCPI Command
Display shows: “Enter P1 measured data”. Enter the data
from the external DVM. This should be about 1 volt. Press
Enter when done. Press Back to finish.
CAL:LEV P1
*OPC?
CAL:DATA <data>
Step 4. After the calibration completes, disconnect the voltmeter and short.
Resistance Bottom-Out Calibration
This procedure calibrates the minimum voltage that can be achieved while sinking current.
Step 1. Connect an external power supply to the + and - output terminals (see
).
Step 2. Set the external supply as follows: Voltage setting = (0.9 V + 0.08 * maximum output voltage of
the unit under test). The voltage must be within 10% of this value. Current limit = (0.95 * rated output
current of the unit under test). The current limit must be within 2% of this value.
Step 3. Select the resistance bottom-out calibration. Calibration takes approximately 5 seconds.
Front Panel Menu Reference
SCPI Command
Select
System\Admin\Cal\Misc\ResBout
. Check that the
power supply is connected and select Next.
Step 4. After the calibration completes, disconnect the power supply.
Enter a Calibration Date
Front Panel Menu Reference
SCPI Command
Select
System\Admin\Cal\Date
.
Enter the calibration date in the Date field. If desired, you
can enter alphanumeric data in this field.
Save Calibration and Log Out
Front Panel Menu Reference
SCPI Command
Select
System\Admin\Cal\Save
.
Select Save to save all calibration data.
Select
System\Admin\Logout
to exit calibration mode.
To save calibration data:
To exit calibration mode:
6 Verification and Calibration
278
Keysight RP7900 Series Operating and Service Guide
Summary of Contents for RP7900 Series
Page 1: ...Keysight Regenerative Power System RP7900 Series Operating and Service Guide ...
Page 2: ......
Page 100: ......
Page 262: ......
Page 314: ......