Kerotest Manufacturing
–
SHANNON & PAF III OPERATORS MANUAL - REV 3
Page 22 of 60
Portafuse III
The
correct power up sequence for the
Portafuse III Electrofusion Processor
depends on whether you are
powering the processor with the battery pack or with the external transformer. The correct sequence for each
scenario is as follows:
Powered with Battery Pack
Powered with External Transformer
1.
Place the battery pack in its mounting bracket
located in the back of the carrying case.
See
page 51 for guidelines on the installation and
removal of the battery pack from its mounting
bracket
.
1.
Attach the output pigtail for the external
transformer to the generator-in connector on
the back of the
Portafuse III Electrofusion
Processor
(see picture on page 14).
2.
Plug the battery pack pigtail into the receptacle
located on the left side of the processor. The
connectors are color coded and should mate
easily with little force.
DO NOT FORCE THE
CONNECTORS TOGETHER.
2.
Start the generator. Make sure the generator is
running smoothly in high speed manual mode.
3.
Rotate the power switch on the left side of the
unit counterclockwise to the ON BATT position
(see page 13). The processor will now boot.
3.
Plug the external transformer into the
generator. Rotate the power switch on the
transformer
clockwise to the ON position.
4.
Rotate the power switch on the
Portafuse III
Electrofusion Processor
clockwise to the ON
GEN position (see page 13). The processor will
now boot.