23
Katherm HK
1.43
Ready-to-install trench heaters with EC tangential fan
Assembly and installation instructions
9.2.4 Additional on-site condensation drainage:
Additional on-site condensation drainage needs to be provided at this
point. The on-site condensation pipe can be fixed by cable ties to the
openings provided by the pre-punched openings in the base to maintain
the necessary gradient.
If a steeper gradient is needed on site for the condensation drain pipe, the
pre-punched openings on the base can be removed as required
6
.
1
Condensate bend
2
Coupling section
3
Hose clamp
4
Cable tie
5
On-site condensation pipe
6
Cut-outs in base (pre-punched)
2
1
3
6
5
4
Fig.: Options to remove sections of the base and routing of on-site condensation drain pipe
Fig.: Additional on-site condensation drain pipe
Fig.: Possible openings needed on the base
6
Room-side
Room-side
Room-side
Room-side
Room-side
Room-side