First, insert the M K2 slot nut into the nut of the Dome SD
and the Dome S1000 and turn 90° clockwise.
Screw the modules at the end of each row with module end
clamps, bolt with serrated under head M8 into the slot nuts.
If the module end and mid clamp set is supplied, fasten the
entire set in the groove.
Use two standard module middle clamps each between two
modules which are also fastened with bolts with serrated
under head M8 screws in the M K2 slot nuts.
Alternatively, XS mid clamps can be used.
However, longer screws must be used in this case.
The length of the cylinder screw with serrated flange is defi-
ned as module frame thi 15 mm when using the XS
middle clamp.
Torque: 14 Nm.
Materials required: Module end/ mid clamp Set
FASTEN MODULE
POSITION MODULE AND FASTEN DOME
SD
The modules are laid horizontally, in the centre of two
Dome D1000s. The specially affixed bars serve as the stop.
Thereafter, the module is positioned on two Dome SDs.
The only loosely fastened Dome SD together with the
protection mat SD 160x180x18 mm are pushed towards
and against the module and then fastened. Before fastening
ensure that the WINGS of the protection mat are under the
Dome SD and the rails at the array edges do not protrude.
Torque: 16 Nm.
Attention: Only modules approved for corner clam-
ping may be used, see point „GENERAL SAFETY IN-
FORMATION“ on page 9. Please take care not to cover
any drainage holes in modules, otherwise potential
condensation cannot run off.
7
of 9
17 | 20
Installation of S-Dome System