Pulsar extractor fan
•
Installation and operating instructions
5.2 Installing the power supply unit (optional)
DANGER
Exposed electrical components.
Electric shock and injury due to live components (230 V, 50 Hz)!
►
Before working on electrical installations, disconnect all affected equipment from the power supply.
►
Do not connect the power supply unit under voltage.
►
The connection must only be performed by qualified and trained personnel.
DANGER
Ingress of water into the Pulsar extractor fan.
Electric shock and overheating due to short circuit (230V, 50Hz)!
►
Create the wall opening for the power supply unit outside protection area 2.
TIP:
The additional power supply unit can only be installed with a 12 V DC electrical connection.A power supply unit
as well as a flush-mounted (plasterboard) box can be ordered as optional accessories.
The installation process described below uses the example of a flush-mounted box. Installation in a flush-mounted plasterboard box
follows the same principle.
Milling drill with ø 68 mm, insulating terminal, filler for plastering in the box
Requirements:
The masonry must be dry and in a load-bearing condition.
There must be no load-bearing elements/electrical wires at the location of the planned borehole/plaster or wall slot.
►
Drill a wall opening, Ø 68 mm, for the flush-mounted
box.
►
Lay the power cable, 230 V AC, to the wall opening for
the flush-mounted box.
►
Lay the operating voltage cable, 12 V DC, between the
opening for the flush-mounted box and the opening for
the Pulsar extractor fan.
Ensure that
the cable end protrudes approximately
300 mm from both wall openings.
Ø
68
INSTALLATION