4 - HANDLING AND INSTALLATION
VIP80E
GB
4 - Pag. 13 / 21
4.8
INSTALLATION PHASES
Below are listed the installation steps. For further details see the relating sections.
Loading axis height variation (section 4.8.1)
Magazine positioning (section 4.8.2)
Alignment and levelling (section 4.8.3)
Bar feeder fastening (section 4.8.4)
4.8.1
Loading axis height variation
The bar feeder is generally supplied with the
loading axis height aligned to that of lathe
spindle. If you need to change it, proceed as
follows:
- Prepare the bar feeder to be lifted (sect. 4.4.).
- Stretch the ropes.
- Loosen, on both sides, the screws (B) and
remove the screws (A).
- Bring the bar feeder to the loading axis height
(see section 2.6. "Loading axis height" table).
- Refit the screws (A) and temporarily adjust
the screws. (B).
Summary of Contents for VIP80 Evolution
Page 2: ......
Page 4: ......
Page 6: ......
Page 35: ...4 HANDLING AND INSTALLATION VIP80E GB 4 Pag 7 21 ...
Page 43: ...4 HANDLING AND INSTALLATION VIP80E GB 4 Pag 15 21 ...
Page 50: ......
Page 56: ......
Page 70: ......
Page 74: ...GB 7 BAR FEEDER MAINTENANCE VIP80E 7 Pag 4 5 Grease Grease ...
Page 76: ......
Page 84: ......