4.6.5 Bar feeder fastening
INFORMATION:
considering that this operation is fundamental to assure in time the bar feeder
stability and the WARRANTY VALIDITY, the person who is authorised to carry it
out, will have to take extreme care of it.
For the positioning proceed as follows.
- Drill the floor in the direction of the plate holes.
Connect the bar feeder to the plates with the tie
rods (H).
- Fasten the plates with expansion plugs.
- Fasten the bar feeder structure to the plates with
the tie rods (H) fastening them with their relative
check nuts.
- Reinstall the two guide sections after making sure
that alignment, levelling and fastening are carried
out correctly.
4.7
BAR FEEDER INSTALLATION (with displacement)
WARNING - CAUTION:
the installation and connections must be carried out according to the indications
provided by the manufacturer. The responsible person will also take into
account all regulative and law requirements, carrying out all the installations
and connections workmanlike. Once the installation has been completed, and
before the operating phases, he will check if the above-mentioned requirements
have been fulfilled.
The installation area must be in adequate environmental conditions (luminosity, ventilation,
etc.).
The floor must be steady and levelled in order to allow a correct fastening of the bar feeder.
If necessary locate the exact position by drawing the coordinates.
Summary of Contents for KID 80-IV Touch
Page 2: ......
Page 4: ......
Page 8: ......
Page 28: ...EN 2 TECHNICAL INFORMATION KID 80 IV 2 Pag 14 18 KID8080_III_02_14_2 ...
Page 37: ...3 SAFETY PROCEDURES GENERAL INFORMATION KID 80 IV EN 3 Pag 5 6 3 6 EC CONFORMITY DECLARATION ...
Page 80: ......
Page 85: ...7 BAR FEEDER MAINTENANCE KID 80 IV EN 7 Pag 5 6 7 3 GREASING POINTS grasso Grease olio Grease ...
Page 92: ......