7 Hoisting an RRU and Related Cables onto a Tower
Issue Draft B (2018-05-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
46
Figure 7-9
Hoisting power cables onto the tower
(1) Lifting sling
(2) Fixed pulley
1.
After climbing up to the tower, installation engineer A secures the fixed pulley to the
tower platform support and leads the lifting sling through the fixed pulley.
2.
Installation engineer B secures three cable ties to the power cable connector, and then
secures the power cable to the lifting sling, as shown in Figure 7-10.
The connector on the power cable in the figure is only an example. The actual connector may vary
according to the situation.