Figure 8-3
Distance between the mounting kits and the ground
As shown in the figure above, it is recommended that the mounting kits be installed at a position 1200
mm (47.24 in.) to 1600 mm (59.06 in.) high above the ground. If the space is insufficient, only the 3.5
Installation Clearance Requirements of an RRU needs to be provided.
Step 2
Install the RRU mounting kits, as shown in Figure 8-4.
Figure 8-4
Installing the RRU mounting kits
Ensure that the arrows on the mounting kits are pointing up.
1.
Adjust the position of the nut and remove the square-neck bolt at the open end from the
slot on the auxiliary bracket.
2.
Slide the mounting kits onto the pole horizontally and insert the square-neck bolt into the
slot.
Step 3
Use a 16 mm (0.63 in.) M10 torque wrench to tighten the nuts to 40 N·m (354.03 lbf·in.) so
that the mounting kits are secured onto the pole, as shown in Figure 8-5.