NetCol5000-A021 In-row Air Cooled Smart Cooling
Product
User Manual (208 V)
3 Installation Guide
Issue 03 (2020-01-10)
Copyright © Huawei Technologies Co., Ltd.
49
Do not drill holes in the floor when routing cables from the top.
Drill holes at the bottom of the raised floor if it is used.
Drill holes based on the actual situation. This prevents mice entering from unnecessary
holes, causing damage to the equipment.
The strong-current cables and the weak-current cables must be routed through separate
holes.
Figure 3-23
Hole position layout (unit: mm)
(1) Bottom active AC1 cable hole, Φ28
mm
(2) Bottom standby AC2 cable hole, Φ28 mm
(3) Bottom refrigerant gas pipe hole, Φ43
mm
(4) Bottom drainpipe hole, Φ43 mm
(5) Bottom refrigerant liquid pipe hole,
Φ43 mm
(6) Bottom humidifier water inlet pipe hole,
Φ43 mm
(7) Top refrigerant gas pipe hole, Φ43 mm (8) Top refrigerant liquid pipe hole, Φ43 mm
(9) Top drainpipe hole, Φ43 mm
(10) Top active AC1 cable hole, Φ28 mm
(11) Top standby AC2 cable hole, Φ28
mm
(12) Top outdoor unit AC3 cable hole, Φ28
mm
Summary of Contents for NetCol5000-A021
Page 234: ......