Figure 6-3 FusionSolar App Quick Guide
6.3.1 Battery Deployment
NO TE
● During system deployment, if the communications cables /Enable– are correctly
connected, the SUN2000 enables the battery and the indicator is on. Do not press the
black start button to enable the battery. Otherwise, the communications cable
connection between the SUN2000 and the battery cannot be verified.
● In cascaded networking scenarios, connect an inverter equipped with energy storage
devices for quick deployment.
Function
Add a battery and set the working mode on the quick settings screen of the
inverter.
Scenario 1: Quick Settings for Single Inverter or Cascaded System Based on
Smart Dongle Networking
Step 1 Log in to the FusionSolar app as installer, tap Setup Wizard, and scan the inverter
QR code (when the Smart Dongle is connected, scan the QR code of the inverter
connected to the Smart Dongle).
LUNA2000-(5-30)-S0
User Manual
6 System Commissioning
Issue 07 (2022-01-10)
Copyright © Huawei Technologies Co., Ltd.
84