8.
9.
Install drives or drive blanks.
11. Slide the server into the rack.
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
The installation is complete.
Installing a rear 2 SFF SAS/SATA drive cage over the power supplies
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
• T-10 Torx screwdriver
• The components included with the hardware option kit
• The front bays are fully populated with 12 LFF or 24 SFF drives
• High-performance fans are installed in all fan bays
Procedure
1.
2.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3.
Do one of the following:
Hardware options installation
114
Summary of Contents for ProLiant DL380 Gen10
Page 33: ...Component identification 33...
Page 58: ...Operations 58...
Page 124: ...7 Install the rear blank from the option kit Hardware options installation 124...
Page 163: ...Box 1 to SAS Expander Box 2 to SAS Expander Cabling 163...
Page 165: ...Box 1 Box 2 Cabling 165...
Page 167: ...Cable routing Midplane 4LFF drive option Cabling 167...
Page 173: ...Cabling 173...