Installation
The following describes the installation of the System hardware.
3.1
System 6844(RC) in 3U / Table-Top / Wall - Housing
3.1.1 Installation of the 19 Inch 3U Rack
The System is assembled in a standard 3U/42HP or 3U/84HP 19" housing for control cabi-
net installation (for dimensions see
Chapter 1.2.2 System Design 6844(RC) in 19 inch
The following steps are to be carried out:
Place the rack in the control panel and fix to the mounting brackets on the front side of
the rack using 4 screws.
The ventilation apertures on the top and bottom sides must not be
covered. Otherwise passive ventilation (convection) will not be effec-
tive and lack of convection and / or thermal coupling with surrounding
equipment may give rise to an excessive equipment operating tem-
perature.
At higher temperatures an active cooling / ventilation is recommended.
Ensure that there is sufficient space between the connection side of the rack and the
control panel to allow for the connection of cables to the System.
3.1.2 Installing the Table-Top Housing