2 Manual Operation and Setup
2.1 S
w
itc
h
-on, S
w
itc
h
-of
f
2.1 Switch-on, Switch-off
Switch-on
Switch on the power supply for control and machine. The TNC
automatically initiates the following dialog
The TNC memory is automatically checked.
TNC message that the power was interrupted —
clear the message.
The PLC program of the TNC is automatically compiled.
Switch on external dc voltage. The TNC checks the
functioning of the EMERGENCY STOP circuit.
Cross the reference points manually in the displayed
sequence: For each axis press the machine START
button, or
Cross the reference points in any sequence: Press
and hold the machine axis direction button for each
axis until the reference point has been traversed.
Switch-on and traversing the reference points can vary
depending on the individual machine tool. Refer to your
machine manual.
MEMORY TEST
POWER INTERRUPTED
TRANSLATE PLC PROGRAM
RELAY EXT. DC VOLTAGE MISSING
MANUAL OPERATION
TRAVERSE REFERENCE POINTS
Summary of Contents for TNC 426
Page 3: ......
Page 4: ......
Page 8: ...IV...
Page 10: ...VI...
Page 26: ......
Page 27: ...1 Introduction...
Page 41: ...2 Manual Operation and Setup...
Page 54: ......
Page 55: ...3 Positioning with Manual Data Input MDI...
Page 59: ...4 Programming Fundamentals of NC File Management Programming Aids Pallet Management...
Page 122: ......
Page 123: ...5 Programming Tools...
Page 153: ...6 Programming Programming Contours...
Page 201: ...7 Programming Miscellaneous functions...
Page 226: ......
Page 227: ...8 Programming Cycles...
Page 366: ......
Page 367: ...9 Programming Subprograms and Program Section Repeats...
Page 381: ...10 Programming Q Parameters...
Page 424: ......
Page 425: ...11 Test run and Program Run...
Page 443: ...12 MOD Functions...
Page 472: ......
Page 473: ...13 Tables and Overviews...
Page 496: ......