5 Commissioning the system – Requirements
100
C
HECK
THE
ELECTRICAL
CONNECTIONS
•
Are all of the sensors and actuators correctly connected and
properly plugged in to the I/O circuit board?
•
Is the mains cable correctly connected (L1 to terminal L1, N to
terminal N)?
•
Has the data cable between the the control system and the
control unit been fitted?
•
Have the unused inputs been bridged?
•
Has the protective earth connection on the circuit board box been
screwed to the body of the boiler?
B
ASIC
SETTINGS
FOR
THE
PRIMARY
AND
SECONDARY
AIR
SUPPLY
The setting knobs to control the primary (1) and secondary (2) air
supply are located behind the left cover of the HDG Pelletmaster 15/
25.
1.
Check the settings of the control knobs.
2.
Adjust the setting as specified in Table 5/1 - Setting of control
knobs.
Danger!
Danger from electrical current or voltage!
Isolate the mains cable to the heating system.
Figure 5/1 - Control of the primary and secondary air supply
1
2
Product
Primary
Secondary
PM 15
8
3
PM 25
8
3
Table 5/1 - Setting of control knobs
Summary of Contents for Pelletmaster 15
Page 1: ...hdg bavaria com HDG Pelletmaster 15 25 Operation Manual V 03 08 2008 ...
Page 2: ......
Page 170: ...170 HDG Pelletmaster 15 25 V 03 en HDG Bavaria GmbH 08 2008 ...
Page 171: ......