CPW 0604 BA CPW 0604 Issue 10.09.13 (From Software-Release 0.0.1.31)
49
4.5.3
Calibration of contact signal
In this section, the procedure of calibration of the contact signal is described.
Insert the original work piece.
Connect the earth clamp.
Move to desired position.
Feed stud:
Selection by touch key „STUD“.
This touch key is active if the green light is displayed.
The green light display shows the currently active condition.
Execution of stud feeding via push buttons confirmation and
START!
Set options (e.g. downholder, spray):
Selection by touch key „Option B“.
This touch key is active if the green light is displayed.
The green light display shows the currently active condition.
Execution of stud feeding via push buttons confirmation and
START!
4 Function
4.5 Menu MANUAL / CONTACT